11-15-23 Chip Fosth Update

Another busy week at Seawatch! This past week the first-floor work continues to progress. They have completed framing the walls in the game room and begun framing on the ceilings. Framing has also started in the outdoor bar area. The electrician has started researching the first-floor connections and installing new lines along with switch boxes.… Continue reading 11-15-23 Chip Fosth Update

Published
Categorized as 2023 News

November 8, 2023 Chip Fosth Update

Valued Seawatch Owners, Another busy week at Seawatch! This past week the first floor continued its resurrection, with continued progress on the ceiling framing & construction. The framing moved out to the ceiling over the pool bar area, & all will soon be ready for the electricians to begin wiring the new lighting. Solarguard is… Continue reading November 8, 2023 Chip Fosth Update

Published
Categorized as 2023 News

October 21, 2023 Update

Good afternoon fellow Seawatch owners, As you know, the rebuilding of Seawatch is well underway. The Board of Directors has agreed upon a professionally designed landscape plan for the property, front, back, and sides. Because most plantings were either lost or destroyed from the hurricane, we were able to design a completely new plan. The… Continue reading October 21, 2023 Update

Published
Categorized as 2023 News

October 11, 2023 Chip Fosth Update

Valued Seawatch Owners, This week we continued to take more steps forward on many roads! Commanche Construction began doing any additional first-floor residual tear out & began framing in the Front Office, Game Room & lobby walls in preparation for doorways, windows, electrical & drywall. New moldings were brought in for finishing any of the… Continue reading October 11, 2023 Chip Fosth Update

Published
Categorized as 2023 News